Calculate Working Days Between 2 Days

Mar 14, 2006

Dear All,

I'm new to VBA coding. A code below is copied from a friend of mine and I can't make it work. How to call up this function in my form. In my form I have 3 text boxes (StartDate, EndDate and NumOfWorkDays). My form is based on a table.

Please anyone who would help me on this, kindly give me the step by step procedure as I am really novice. Thanks in advance.

'*********** Code Start **************
Public Function WorkingDays(StartDate As Date, EndDate As Date) As Integer
On Error GoTo Err_WorkingDays

Dim intCount As Integer

StartDate = StartDate + 1
'If you want to count the day of StartDate as the 1st day
'Comment out the line above

intCount = 0
Do While StartDate <= EndDate
'Make the above < and not <= to not count the EndDate

Select Case WeekDay(StartDate)
Case Is = 1, 7
intCount = intCount
Case Is = 2, 3, 4, 5, 6
intCount = intCount + 1
End Select
StartDate = StartDate + 1
Loop
WorkingDays = intCount

Exit_WorkingDays:
Exit Function

Err_WorkingDays:
Select Case Err

Case Else
MsgBox Err.Description
Resume Exit_WorkingDays
End Select

End Function
'xxxxxxxxxxxxxxxxxxxxxxxx

Can someone please direct me to the right path.

Your help is highly appreciated.

qwerty70

View Replies


ADVERTISEMENT

Calculate Working Days

May 11, 2007

I hope you can help. I have a database and I am trying to work out the working days between the start date and the end date of a programme. This will not take into account any weekends or bank holidays. I have created a separate table called tblHolidays which has a list of the Bank Holidays. The majority of it works but out of 1700 records 50 don’t. These are ones in which it starts on 1 month finished on another or has a bank holiday. It works with certain bank holidays but not all of them. Bank holidays go back to the beginning of 2006
The following is the code I have used:
Public Function WorkingDays2(Start_Date As Date, End_Date As Date) As Integer

On Error GoTo Err_WorkingDays2

Dim intCount As Integer
Dim rst As DAO.Recordset
Dim DB As DAO.Database

Set DB = CurrentDb
Set rst = DB.OpenRecordset("SELECT [HolidayDate] FROM tblHolidays", dbOpenSnapshot)

Start_Date = Start_Date + 1

intCount = 0

Do While Start_Date <= End_Date

rst.FindFirst "[HolidayDate] = #" & Start_Date & "#"
If Weekday(Start_Date) <> vbSunday And Weekday(Start_Date) <> vbSaturday Then
If rst.NoMatch Then intCount = intCount + 1
End If

Start_Date = Start_Date + 1

Loop

WorkingDays2 = intCount

Exit_WorkingDays2:
Exit Function

Err_WorkingDays2:
Select Case Err

Case Else
MsgBox Err.Description
Resume Exit_WorkingDays2
End Select

End Function

I then used the SQL

Select WorkingDays2 ([start_Date], [End_Date]) As CountDays

This is driving me crazy!!:mad:

View 12 Replies View Related

Trouble Implementing The Regular Days And Sunday Working Days?

Dec 14, 2004

Hello everyone,

I have problem with my code here. I am using this code to determine if the LogDate with a weekday of Sunday can be declare as Sunday Work or Regular Work. The 1st week of my entry can determine if the LogDate is Sunday then compute if it reaches a 7 days working, if he is absent even 1 (one) day in his previous working days within the week. His Sunday LogDate is considered as Regular Days instead of Sunday Work. Can anyone tell me what is wrong in this code?

The problem here is the computation of 7 days after 1 week. There should be a 7 days computation every week per month in able to declare Sunday Work or Regular Work. I tried this code but it did not work on 2nd week, 3rd week and 4th week of the month.

How come on 2nd week, Sunday (LogDate) is not considered as Sunday Work even he completed the 7 days (working days) per week? I need help on this ASAP Thanks

Tim

Below is the code i'm using for defining Regular days and Sunday Working Days:


Private Sub LogDate_AfterUpdate()
Dim rst As DAO.Recordset, rs As DAO.Recordset
Dim db As DAO.Database
Dim dteToday As Date, dtePrior As Date
Dim i As Integer

dteToday = LogDate
dtePrior = DateAdd("d", -6, dteToday)

Set db = CurrentDb
Set rst = db.OpenRecordset("SELECT [HolidayDate] FROM tblHolidays", dbOpenSnapshot)

rst.FindFirst "[HolidayDate] = #" & dteToday & "#"
'See if the date entered is a holiday
If rst.NoMatch Then
Holiday.Value = 0
Else
Holiday.Value = 1
End If
If Weekday(dteToday) = vbSunday Then 'If dated entered is a Sunday determine if
Dim strSQL As String 'it will be a regular day or a Sunday

strSQL = "SELECT [LogDate] "
strSQL = strSQL & "FROM tblLog "
strSQL = strSQL & "WHERE [LogDate] >= #" & dtePrior & "#"
strSQL = strSQL & " AND [LogDate] <= #" & dteToday & "#"

'Create a recordset of records from date entered and 7 days prior
Set rs = db.OpenRecordset(strSQL, dbOpenSnapshot)

rs.MoveLast
i = rs.RecordCount 'Count the number of days between the two dates

If i = 7 Then 'If there are seven days then it is a Sunday
Sunday.Value = 1
Else
Sunday.Value = 0 'If less than 7 days then it is a regular day
End If

Else
Sunday.Value = 0
End If

DayofWeek.Value = Format(dteToday, "dddd")

End Sub

View 1 Replies View Related

Date Add Problem (calendar Days Vs Working Days)

Dec 4, 2006

I have a query and I need the records to display 3 working days before the 15 working day deadline.

I used the following in the criteria box below the received date field and it doesn't pull the correct number of workdays, it's pulling calendar days instead.

<=DateAdd("w",-12,Date())

Can anyone help, thanks for your time!!!

View 8 Replies View Related

Date Add Problem (calendar Days Vs Working Days)

Dec 4, 2006

I have a query and I need the records to display 3 working days before the 15 working day deadline.

I used the following in the criteria box below the received date field and it doesn't pull the correct number of workdays, it's pulling calendar days instead.

<=DateAdd("w",-12,Date())

Can anyone help, thanks for your time!!!

View 6 Replies View Related

Calculate Days In Advance Or Days In Arrears

Dec 26, 2006

I rent out a property , on the rental statement I have a field [Datepaid], [RentpaidFrom] and [rentpaidTo]. I would to have a field that can calculate the rent that is paid to show if the rent is in arrears or in Advance. I guess the code would be something like (datediff ???? etc) but i have no idea what it should be. the calculation should appear on the query as i.e.2 days in arrears or 12 days in advance etc

your help would be much appreciated

merry christmas to you all
Jabez

View 4 Replies View Related

Forms :: Calculate Passed Working Days And Show Them In A Form

Jul 8, 2015

I need to calculate the passed working days and show them in a form. I should be also able to use the number in a query later on. in excel I use the formula to get the days passed:

Code:
=IF(ISERROR(MATCH(F10,Dictionary!C:C,0)),NETWORKDAYS(D10, TODAY(), Dictionary!$E$2:$E$43),"Status Excluded")
D = "Date_uploaded" in access table "tbl_All_Cases"
F = "Status_Case" in access table "tbl_All_Cases"
c:c = dictionary case status
E:E = dictionary holidays

"Status Excluded" will show up in the cell if a case has one of the status from the dictionary..I created a table: tbl_Dictionary where there are 2 fields: "Case_Status" and "Holidays".How can I translate the above formula into something that access will understand?

View 14 Replies View Related

Queries :: Counting Days Between Dates - Vacation Period And Work Days

Sep 11, 2014

I have a form called subfrm_vactions

rowsource is a query called qryVacations

the query should calculated two things

1 - the difference between start_vac and End_vac in days to calculate the vacation period and put the value in field called Period (working well)

2-the work days which the period between the last day in Previous record (End_Vac) and the (Start_Vac) in the next record (didn't work)

the result is the difference between (End_Vac) and (Start_Vac) in the same record which i don't want

simply i want to calculate the work days.

View 5 Replies View Related

Reports :: Count Number Of Days Each Week (7 Days) Person Has Worked

Jan 24, 2014

I have to count the number of days each week (7 days) that a person has worked - simple enough.

But - what if they come off the job within the week?

I have been using the DateDiff function which is fine.

In the database they have a Mobdate and a DeMobDate but if the DeMobDate falls within the week the whole thing falls apart?

View 2 Replies View Related

General :: Convert Weekend And Holiday Days To Work Days

Jun 14, 2013

Is there a way i can convert the weekend days into working days for example.

5/4/13 1:30 PM is on saturday what function can I use to make this day read 5/6/13 8:00 Am which is monday. Same thing for holidays.

View 1 Replies View Related

Queries :: Number Of Days Between Two Dates With Irregular Days Worked

Apr 14, 2014

I have a form where a start date is inputted (Inputfrm , StartDate) and a form where the end date of the process is recorded (Inspectionfrm , EndDate) and these both record in the table InputTbl as StartDate and EndDate respectively.

I have created a union query which shows a list of all the dates where there is work recorded (WorkingDatesQry and the column of list of unique dates is "WorkingDate"), and as we run a highly varied schedule depending on time of the year and order numbers I cannot just use a query which says Monday-Friday or Tuesday - Saturday.What I am trying to do is to find the number of days between StartDate and EndDate where there is a date recorded in the WorkingDates query.

View 1 Replies View Related

Queries :: Missing Days - Creating Table With 31 Days Of Zero Values

Apr 3, 2013

Client has asked me to create a report showing summary of monthly sales by day. That was easy. I created a query for the month the user selected and then summarized and group the data by day. Client like the result but would like to see zeros on the report for non sales days. Non sales days are days like holidays and there are no sales.

I am thinking of creating an table with 31 days of zero values and then join the two tables in a query? Or, should I create a temporary table with code and then merge the two tables which the existing query which I can then use for the report?

View 4 Replies View Related

Calculate Number Of Days

May 4, 2006

In a database, I have the following date fields that I use to track projects that start and stop.

START1
STOP1
START2
STOP2
START3
STOP3

Is there a way I can use a query to calculate the total days the project was worked on? For example if I enter 1/1/06 in START1, 1/10/06 in STOP1, 2/1/06 in START2 and 2/15/06 in STOP2, 3/1/06 in START3 and 3/30/06 in STOP3, I need to calculate the total days. I need it to work regardless if there are 3 start/stops, 2 or just one start/stop.

I really appreciate the help.

Jim

View 14 Replies View Related

Calculate Days When There Are 4 Variables

Jul 7, 2006

I have a query that has four date variables:

Admit Date
Discharge Date
Report Begin Date
Report End Date

I can calculate the number of days with the DateDiff function when the "Admit Date" and "Dischage Date" are within the range of the report with no problem.

The problem arises when the "Admit Date" is prior to the "Report Begin Date". In this case, the difference needs to be "Report Begin Date" and "Discharge Date".

To make this more complicated, in some cases there is no "Discharge Date", so the calculation needs to look at the first two senerio's and then calculate the days based on the "Report End Date".

Expr2: IIf([Admission Date]<[Beginning of Report],DateDiff("d",[Beginning of Report],[D/C Date / Time]),DateDiff("d",[Admission Date],[D/C Date / Time]))


Expr2: IIf([Admission Date]<[Beginning of Report] And [D/C Date / Time]>[End of Report],DateDiff("d",[Beginning of Report],[D/C Date / Time]),DateDiff("d",[Admission Date],[D/C Date / Time]))

Expr3: IIf(IsNull([D/C Date / Time]) And [Admission Date]<[Beginning of Report],DateDiff("d",[Beginning of Report],[End of Report]),DateDiff("d",[Admission Date],[End of Report]))

expr4: IIf([Admission Date]>[Beginning of Report],DateDiff("d",[Admission Date],[D/C Date / Time],0))

Above are failed attempts to get the formula right.

Can anyone assist me in getting this to work correctly.

Thanks
Dan:mad:

View 9 Replies View Related

Calculate Only Business Days

Feb 10, 2005

I have a date range of 1/01/2005 to 12/25/2005 for example. I need a formula to return the number of days between these dates excluding weekends. Basically I need to know how many business days are between these dates. Thanks for the help.

View 1 Replies View Related

Calculate Days Between Billing Dates

Oct 6, 2005

I am woking on a project full of nightmares. My latest, and the one I am currently unable to solve, involves trying to calculate the number of days between Billing Dates.

I have a table named "Date" - I didn't design this!
It contains a field named "Date"

If I query for just that Field I get the following:
Date
9/8/2005
8/8/2005
7/8/2005
6/8/2005
5/9/2005
...

I need to figure out a way to determine the number of days between the bills so I can calculate the average cost per day.

It seems like it should be an easy thing using like the datediff function or something, but since they are in separate records (rows), I can't figure it out. I have tried and tried and tried.

Any suggestions would be VERY much appreciated.

View 3 Replies View Related

Calculate Days Between Dates & Other Criteria

Dec 9, 2007

I have a database with 10-12 fields containing dates certain things were completed. There is also a field for the 3 different locations we have and a program year 2006, 2007, or 2008. What they would like to do is click a button and get a list to choose the first date they which to compare, then a list to choose the second date, calculate the number of days between the two dates, select the program year from a list, and a location from a list. Can anyone help me with how to do this if it's possible?

The fields look something like this:

Prog Year Location DateA Date B DateC DateE
2006 G date date date date
2006 G date date date date
2006 P date date date date
2008 D date date date date
2007 P date date date date

For Example, I might want 2006 Program Year, Location P, calculating days between DateA and DateB, except that the next time I might want to choose a different set of criteria.

Any ideas?

THANK YOU!

View 7 Replies View Related

Getting DateDiff To Calculate Half Days

Jun 8, 2006

I have an access database used for recording training events. I was able to calculate the number of days each training event took by using

Datediff("d",[Training Date From],[Training Date To]+1)

I was really chuffed with this until my boss asked what happens when the training only lasts half a day! I added the time to the above fields to make them date/time fields but can't see a way to calculate in half days.

As well as this the other problem is that training could be over a few days. As an example I'd like to be able to input that the training started at 9am on Monday 29th May and ended at 12 noon on Thursday 1st June and get the result of 3.5 days. The full days would all end at 5pm but I wouldn't be recording that, just the total days. I tried changing the datediff function to hours in the hope I could somehow discount the non working hours but that didn't work! I'd ideally like the final result to be in days, ie 0.5, 1 etc. It would always be in whole or half day increments - don't need things to be overly complicated!

Any help will be very gratefully received. I'm definitely not an expert as you can probably tell!! :eek:

View 1 Replies View Related

General :: Calculate Days Using 2 Arguments

Dec 18, 2012

I have a database to monitor incoming emails from our contractor & my superior wants it to have control like the following situations:

1. If no respond yet, to calculate today's date minus received date
2. If responded, to calculate respond date minus received date

If i use the following expression, it does not relate to if the emails have no respond yet or have been responded.

IIf(IsNull([Reply Date]),DateDiff("d",[Due Date], Now()))

View 4 Replies View Related

Calculate How Many Weekend Days Are Between 2 Dates

Aug 17, 2015

I'm trying to create a sub to count how many days between 2 dates excluding Holiday and weekend. Using the DateDiff() function is not allowing me to exclude certain days.

View 2 Replies View Related

Working Days

May 10, 2005

Can anyone help
I have one field that you enter a start date
the next field is the start date that adds 28 days to give a due date
but this includes saturdays and sundays which i dont want i only want the working week/day.
Please help

View 3 Replies View Related

Working Days

May 22, 2005

In my queries i have two fields

1st Field is called Termination Date
2nd Field is called Due Date:
3rd Field is called Date Completed:
4th Field is called (+/-):

Termination Date = I enter a date such as 20/05/05
Due Date = Automatically fills in using the expression below 17/06/05
The Due Date has an expression builder i.e.
Termination Notice-Due Date: [Termination Date]+28

Date Completed = I enter a data such as 18/06/05
(+/-) = Automatically fills in with -1

The problem is that Termination Notice-Due Date Automatically filled in using the above expression but it counts saturdays and sundays i dont want saturdays and sundays counted in the +28

Can this be done or iam i going nuts

please see attached this might help


Hazel

View 4 Replies View Related

Working Days

May 16, 2007

I recently ran into a problem calculating working days, i now have it working however i have a couple of other issues that i would like some assistance with.
I am looking to introduce a seperate field which would say eitehr YEs or NO if the entry is more than 5 days old. SO i know how many are over 5 days. But whenever i use > 5 i get Data type mismatch. How do i get round this. :mad:

View 1 Replies View Related

Add Only Working Days

Nov 16, 2005

Help please, im using this code

Private Sub Target_Combo_AfterUpdate()
Select Case Target_Combo
Case "Emergency"
Me.TARGET_COMPLETION_DATE = Me.ISSUE_DATE
Case "3 Days"
Me.TARGET_COMPLETION_DATE = DateAdd("d", 3, Me.ISSUE_DATE)
Case "3 Weeks"
Me.TARGET_COMPLETION_DATE = DateAdd("d", 21, Me.ISSUE_DATE)
Case "28 Days"
Me.TARGET_COMPLETION_DATE = DateAdd("d", 28, Me.ISSUE_DATE)
Case "2 Months"
Me.TARGET_COMPLETION_DATE = DateAdd("m", 2, Me.ISSUE_DATE)
Case "4 Months"
Me.TARGET_COMPLETION_DATE = DateAdd("m", 4, Me.ISSUE_DATE)
Case "6 Months"
Me.TARGET_COMPLETION_DATE = DateAdd("m", 6, Me.ISSUE_DATE)
End Select
End Sub




But i want it to add only working days (monday to friday) so if i added 3 working days on to fridays date then the date would be for wednesday

View 2 Replies View Related

Calculate Days Open Based On Status

Mar 21, 2006

I am not sure if what I am about to ask is best done in a query, table or report, so I thought I would post this in the query section of the forum.

I have a table that contains the following fields (plus other fields)

RC_START_DATE
RC_DUE_DATE
RC_APPROVAL_DATE
RC_STATUS

On one of my reports, I want to show the "Days Open". If the RC_Status is "Active" I want to calculate the "Days Open" by subtracting RC_START_DATE from Today(). However if the RC_Status is "Closed" I want the "Days Open" to be calculated by RC_APPROVAL_DATE minus RC_START_DATE.

So the question is, what is the best way to do this and how would I write the formula to calculate this?

Thanks for the help.

Jim

View 6 Replies View Related

Tables :: Calculate Remaining Days In A Table

Feb 11, 2013

I'm trying to step from Excel to Access and I have some issues to translate functions that I used in Excel to Access.This is how it looks in Excel.And I have issues to translate the following function in Excel to Access.

=IF(AND(I6=0),"Done",K6-A$4)

A$4 is related to cell where it states the function =now() Basically what I want is to calculate in the tablecolumn is the following.In the column "Days remaining" I want the remaining days from "date to pay" and today. If the amount states "0" then the outcome must be "done".