Queries :: Function To Calculate Date Diff In Network Days
Aug 7, 2014
I'm using the following function to calculate date diff in network days (excluding weekends)
Public Function NetWorkdays(dteStart As Date, dteEnd As Date) As Integer
Dim intGrossDays As Integer
Dim dteCurrDate As Date
Dim i As Integer
intGrossDays = DateDiff("d", dteStart, dteEnd)
NetWorkdays = 0
[Code] ....
So when using this function in a query to get number of networkdays between 2 date columns ...it works fine but throws a #Error where there is blank entries in either of 2 date columns...
I need to find a way to display Null instead of #Error...
I have tried this expression but no luck...
IIf(IsError(NetWorkdays([Date1],[Date2])),"",NetWorkdays([Date1],[Date2]))
View Replies
ADVERTISEMENT
Jun 12, 2014
How to amend the below, so that instead of doing 4 days, it does 4 working days?
<=DateAdd("d",4,Date())
View 5 Replies
View Related
Jan 20, 2014
Looking to have a count function which calculate data in sense like if records found on 1-jan-2014 the it give answer as 1, same as records for 2-jan-2014 it should return 2 and so on .. in short the criteria must look and give same number for same dates starting from 1
View 8 Replies
View Related
May 18, 2013
I am trying to calculate how many days are left till end of contract...
whats wrong with this formula
=DateDiff("d",[Completion_Date], Date())
View 14 Replies
View Related
Jul 22, 2014
I have written a user defined function that calculates the end of the current month. This I named EndOfThisMonth. It works well as a function. Now I would like to use it as date criteria to include in a query. The function is included as such EndOfThisMonth().
The field on which this function is to enter as a criteria is another calculated date function called Due.
When I run this query I get an error message saying Undefined Function 'EndOfThisMonth' in expression.
View 3 Replies
View Related
Jun 30, 2015
I need to calculate the final date based on the begin date and the number of days.
The name of the fields are: sdatainicio; diasatribuidos; sdatafim.
View 7 Replies
View Related
Jan 28, 2013
What's the formula we can use to calculate days between no of days between date job is open and today's date in a query. I am using formulat below formula but the DATE_OPEN and Today (todays date) pops us as enter parameter value. I dont want those enter parameter windows pops us. The date job is open is in a linked table and linked table is getting the information from BPCS software. The date in Liinked is in format YYYYMMDD.
Total Days: DateDiff("d",[Date_Open],[Today])
The SQL Details are below. AUNPRDF_AAA802 is a linked table and information gets updated on 12 am everyday
SELECT DateDiff("d",[Date_Open],[Today]) AS [Total Days], AUNPRDF_AAA802.AAAGE AS Age, AUNPRDF_AAA802.AAORD AS [Job Number], AUNPRDF_AAA802.AAWKSP AS Workshop,
AUNPRDF_AAA802.AASWKT AS WorkType, AUNPRDF_AAA802.AANAME AS [Customer Name], AUNPRDF_AAA802.AANME AS [Service Admin], AUNPRDF_AAA802.AASDE1 AS Complaint,
[Code] ....
View 7 Replies
View Related
Oct 17, 2013
I am having a problem with a datediff expression.I have a query that pulls the first date and the last date out of a list but are put in seperate fields. I thought I could build an expression for datediff to calculate the number of dates between them. I can't just put in the dates because they are constently changing.The expression I have is:
[datediff("d",[min/max edging unit #2]![firstofupdate/time by month],[min/max edging unit #2]![lastofupdate/time by month])]
View 4 Replies
View Related
Nov 21, 2014
I'm trying to calculate the number of days between two dates using the iif statement
Fields:
[LDW] "Last Day Worked"
[ReturnedDate]
DESCRIPTION: If ReturnedDate is null, then calculate the datediff "d" between LDW with Now(), if not, then calculate the datediff "d" between LDW with ReturnDate.
I tried this but it didn't work at all.
Days Absent: Iif(isnull([ReturnedDate],(DateDiff("d",[LDW],Now())),(DateDiff("d",[LDW],[ReturnedDate])))
View 2 Replies
View Related
Feb 18, 2015
Basically I have a report that shows any 'Issues' that wasnt closed within the KPI Target.
I have the report working, but I simply want to do a count of how many days the observations overran the 'Target Date of Closure'.
The report also shows observations that are not closed but passed their Target Date of Closure. These observations will not have a 'Actual Closure Date', but I would like to still have a count of how many days its overrun closure.
This is a formula I tried to piece together but obviously not correct as it's not returning anything;
IIf(IsNull([Issues]![Actual Closure Date]),DateDiff("d",[Issues]![Target Date of Closure],
Date()),DateDiff("d",[Issues]![Target Date of Closure],[Issues]![Actual Closure Date]))
View 2 Replies
View Related
Dec 26, 2006
I rent out a property , on the rental statement I have a field [Datepaid], [RentpaidFrom] and [rentpaidTo]. I would to have a field that can calculate the rent that is paid to show if the rent is in arrears or in Advance. I guess the code would be something like (datediff ???? etc) but i have no idea what it should be. the calculation should appear on the query as i.e.2 days in arrears or 12 days in advance etc
your help would be much appreciated
merry christmas to you all
Jabez
View 4 Replies
View Related
Mar 12, 2015
i have 2 tables.. 1 with bookings and 1 with a BonusPeriod range.
in the Bookings table there is a field called [ServiceDate]
in the bonus table i have a field called [Period] which is text i also have 2 dates, [StartDate] And [EndDate] i need to Dlookup the Bonus table to return the value of the period table based on where the [ServiceDate] falls.
i dont want to use VBA (i really need it to work within a query that inserts it's data into another table)
i've tried everything but had no joy
Expr1: DLookUp("[Period]","BonusPeriods","[ServiceDate]" Between "#[StartDate]#" And "#[EndDate]#")
Expr1: DLookUp("[Period]","BonusPeriods","[Staff_BookingsAndQuotes_Master].[ServiceDate]" Between "#[StartDate]#" And "#[EndDate]#")
Expr1: DLookUp("[Period]","BonusPeriods","(FormatDateTime([ServiceDate]),"yyyy-mm-dd") Between (FormatDateTime([BonusPeriods]![StartDate]),"yyyy-mm-dd") and (FormatDateTime([BonusPeriods]![EndDate],"yyyy-mm-dd"))))
View 10 Replies
View Related
Mar 14, 2006
Dear All,
I'm new to VBA coding. A code below is copied from a friend of mine and I can't make it work. How to call up this function in my form. In my form I have 3 text boxes (StartDate, EndDate and NumOfWorkDays). My form is based on a table.
Please anyone who would help me on this, kindly give me the step by step procedure as I am really novice. Thanks in advance.
'*********** Code Start **************
Public Function WorkingDays(StartDate As Date, EndDate As Date) As Integer
On Error GoTo Err_WorkingDays
Dim intCount As Integer
StartDate = StartDate + 1
'If you want to count the day of StartDate as the 1st day
'Comment out the line above
intCount = 0
Do While StartDate <= EndDate
'Make the above < and not <= to not count the EndDate
Select Case WeekDay(StartDate)
Case Is = 1, 7
intCount = intCount
Case Is = 2, 3, 4, 5, 6
intCount = intCount + 1
End Select
StartDate = StartDate + 1
Loop
WorkingDays = intCount
Exit_WorkingDays:
Exit Function
Err_WorkingDays:
Select Case Err
Case Else
MsgBox Err.Description
Resume Exit_WorkingDays
End Select
End Function
'xxxxxxxxxxxxxxxxxxxxxxxx
Can someone please direct me to the right path.
Your help is highly appreciated.
qwerty70
View 1 Replies
View Related
Apr 22, 2013
I am trying to calculate the difference in dates between two fields. How do I find the difference in days between field one which contains the date 04/12/2011 and field two which contains the date 04/12/2013? I have tried to use the datediff function, but it keeps telling me it doesn't recognize the field name, even though the spellings correct.
View 3 Replies
View Related
Jul 29, 2015
Is there a way to replicate NETWORKDAYS formula in Excel to Ms Access?
View 2 Replies
View Related
May 7, 2013
I am using the following expression to calculate a completion date for a project which is based on the due date. My problem that I am running into is when I get to a project that is due on a Tuesday, it returns a date for Sunday when it should be Friday.
IIf(Weekday([Due Date])=2,DateAdd("d",-4,[Due Date]),DateAdd("d",-2,[Due Date]))
View 3 Replies
View Related
Aug 4, 2013
In a query i have setup, i work out when a tenant is next due to pay their rent.
Looks like this
Tenant Last Payment Date Payment Terms Next Payment Date
User1 01/07/13 Monthly 01/08/13
User2 01/07/13 Weekly 07/07/13
The next payment date is calculated using an IF statement and DateAdd in the query, so if it is weekly it adds 7 days, if it is monthly it adds 1 month.
What i am trying to do is write sub query of this one which shows which tenants are due to pay within the next 7 days.
But the access query seems to ignore the criteria I'm putting in....in the next payment date criteria i have tried specifying >Now() + 7 or >Date() +7 but neither seem to work, it just shows up every record...
View 6 Replies
View Related
Mar 10, 2014
I have a large database filled with customer records. Some customers come one time. Other customers come 50 times at year. I want to find all customers that have records that are less than 30 days apart so I can ultimately see the types of products they buy. How do I write the query?
I attached a picture of a sample database. The 30 day (+/-) field doesn't exist but I would like the query results to build it.
View 11 Replies
View Related
Mar 22, 2015
Ok, so I'm sure this is a pretty simple criteria, but I just can't seem to get the syntax right.
I'm trying to allow my user to select any start date and the query will return that date plus the next three days.
View 7 Replies
View Related
Aug 11, 2014
I'm trying to build a query that adds up the total sales for a given product per date. The problem I'm running into is some products have $0 sales on a given day and don't appear in the table I'm querying. How would I get the query to add a record for that day for the given product with 0 in the sales field?
To give more details, I currently have one table showing the sales data. It has a record for every sale that includes the product of the sale, the amount, and the date. In the query, I'm summing the sales for a given day and product. Then I plan to export to Excel where I will run additional analysis.
If there are no sales for the product in a day, I'd like it to list the date and product with a $0 in the sales column.
View 5 Replies
View Related
Feb 7, 2015
I'm working on a query ("Target Date of Completion") that takes the initial date started (from Step 1 of date started) and adds the EC (Estimated Completion) which is just shown in days. This will give an EST (Estimated Start time) for the next step in date format, which I would need the new column. Also, As you can see, the piece parts all have a different amount of steps, so this calculation would need to know when it's a different part.
View 7 Replies
View Related
Mar 5, 2014
I have a query call courses and field name expiry date I have add additional field within the query to show how many day left and how many days over the expiry date
Code : DayLeft:[expirydate]-now()
but i just get a error when i run the query
I also would like to ask is this possible to be done within the table e.g adding another field dayleft and some how add formula to calculate number days left or over due .
View 2 Replies
View Related
Dec 4, 2006
I have a query and I need the records to display 3 working days before the 15 working day deadline.
I used the following in the criteria box below the received date field and it doesn't pull the correct number of workdays, it's pulling calendar days instead.
<=DateAdd("w",-12,Date())
Can anyone help, thanks for your time!!!
View 8 Replies
View Related
Dec 4, 2006
I have a query and I need the records to display 3 working days before the 15 working day deadline.
I used the following in the criteria box below the received date field and it doesn't pull the correct number of workdays, it's pulling calendar days instead.
<=DateAdd("w",-12,Date())
Can anyone help, thanks for your time!!!
View 6 Replies
View Related
May 4, 2006
In a database, I have the following date fields that I use to track projects that start and stop.
START1
STOP1
START2
STOP2
START3
STOP3
Is there a way I can use a query to calculate the total days the project was worked on? For example if I enter 1/1/06 in START1, 1/10/06 in STOP1, 2/1/06 in START2 and 2/15/06 in STOP2, 3/1/06 in START3 and 3/30/06 in STOP3, I need to calculate the total days. I need it to work regardless if there are 3 start/stops, 2 or just one start/stop.
I really appreciate the help.
Jim
View 14 Replies
View Related
Jul 7, 2006
I have a query that has four date variables:
Admit Date
Discharge Date
Report Begin Date
Report End Date
I can calculate the number of days with the DateDiff function when the "Admit Date" and "Dischage Date" are within the range of the report with no problem.
The problem arises when the "Admit Date" is prior to the "Report Begin Date". In this case, the difference needs to be "Report Begin Date" and "Discharge Date".
To make this more complicated, in some cases there is no "Discharge Date", so the calculation needs to look at the first two senerio's and then calculate the days based on the "Report End Date".
Expr2: IIf([Admission Date]<[Beginning of Report],DateDiff("d",[Beginning of Report],[D/C Date / Time]),DateDiff("d",[Admission Date],[D/C Date / Time]))
Expr2: IIf([Admission Date]<[Beginning of Report] And [D/C Date / Time]>[End of Report],DateDiff("d",[Beginning of Report],[D/C Date / Time]),DateDiff("d",[Admission Date],[D/C Date / Time]))
Expr3: IIf(IsNull([D/C Date / Time]) And [Admission Date]<[Beginning of Report],DateDiff("d",[Beginning of Report],[End of Report]),DateDiff("d",[Admission Date],[End of Report]))
expr4: IIf([Admission Date]>[Beginning of Report],DateDiff("d",[Admission Date],[D/C Date / Time],0))
Above are failed attempts to get the formula right.
Can anyone assist me in getting this to work correctly.
Thanks
Dan:mad:
View 9 Replies
View Related