I need to work out a couple of calculations, the number of days between an engineer starting and finishing a project, the number of days between the project being put on the database in the first place and being completed by an engineer and finally, the difference between these. These maybe simple, but I have no idea tbh (still new to access).
I have a form with the date it was added onto the database, and the engineer fills in the date started and date finished as it happens.
These run off of 2 tables BookingIntbl and TechnicalServicestbl
[BookingIntbl].[Date], [TechnicalServicestbl].[Date Started] and [TechnicalServicestbl].[Date Finished]
I have then got the fields, 'Days with Engineer', 'Days in Repair Centre' and 'Day Difference' for the answers to be displayed.
I have a form where a start date is inputted (Inputfrm , StartDate) and a form where the end date of the process is recorded (Inspectionfrm , EndDate) and these both record in the table InputTbl as StartDate and EndDate respectively.
I have created a union query which shows a list of all the dates where there is work recorded (WorkingDatesQry and the column of list of unique dates is "WorkingDate"), and as we run a highly varied schedule depending on time of the year and order numbers I cannot just use a query which says Monday-Friday or Tuesday - Saturday.What I am trying to do is to find the number of days between StartDate and EndDate where there is a date recorded in the WorkingDates query.
I want the number of days between a specific date (roll out date) and 12/31/2005 so that I can use the number to project revenue for this year.
This is what I'm using but it doesn't give me the right number. I don't know how to transform something to a datetime variable so maybe that's the reason. Can you help me out?
Expr4: Day(12/31/2005-[Scheduled Roll Out Date]-0.49999)
I am making a basic hospital management system in Access 2013.I have two tables named "Bed" and "Receipt". Bed(BedID,AssignedDate,PatientID,DischargeDate,Bed Charges) Reciept(ReceiptID,PatientID,BedCharges) I want to calculate "BedCharges" by calculating the number of days using "AssignedDate" and "DischargeDate" and then multiplying with a constant amount of charges per day. Also the BedCharges calculated in "Bed" Table also needs to be in the "Receipt" table. How can I count the number of days and then calculate the "BedCharges" in both the tables?
I'm trying to calculate the number of days between two dates using the iif statement
Fields: [LDW] "Last Day Worked" [ReturnedDate]
DESCRIPTION: If ReturnedDate is null, then calculate the datediff "d" between LDW with Now(), if not, then calculate the datediff "d" between LDW with ReturnDate.
I tried this but it didn't work at all.
Days Absent: Iif(isnull([ReturnedDate],(DateDiff("d",[LDW],Now())),(DateDiff("d",[LDW],[ReturnedDate])))
Basically I have a report that shows any 'Issues' that wasnt closed within the KPI Target.
I have the report working, but I simply want to do a count of how many days the observations overran the 'Target Date of Closure'.
The report also shows observations that are not closed but passed their Target Date of Closure. These observations will not have a 'Actual Closure Date', but I would like to still have a count of how many days its overrun closure.
This is a formula I tried to piece together but obviously not correct as it's not returning anything;
IIf(IsNull([Issues]![Actual Closure Date]),DateDiff("d",[Issues]![Target Date of Closure], Date()),DateDiff("d",[Issues]![Target Date of Closure],[Issues]![Actual Closure Date]))
I am woking on a project full of nightmares. My latest, and the one I am currently unable to solve, involves trying to calculate the number of days between Billing Dates.
I have a table named "Date" - I didn't design this! It contains a field named "Date"
If I query for just that Field I get the following: Date 9/8/2005 8/8/2005 7/8/2005 6/8/2005 5/9/2005 ...
I need to figure out a way to determine the number of days between the bills so I can calculate the average cost per day.
It seems like it should be an easy thing using like the datediff function or something, but since they are in separate records (rows), I can't figure it out. I have tried and tried and tried.
I have a database with 10-12 fields containing dates certain things were completed. There is also a field for the 3 different locations we have and a program year 2006, 2007, or 2008. What they would like to do is click a button and get a list to choose the first date they which to compare, then a list to choose the second date, calculate the number of days between the two dates, select the program year from a list, and a location from a list. Can anyone help me with how to do this if it's possible?
The fields look something like this:
Prog Year Location DateA Date B DateC DateE 2006 G date date date date 2006 G date date date date 2006 P date date date date 2008 D date date date date 2007 P date date date date
For Example, I might want 2006 Program Year, Location P, calculating days between DateA and DateB, except that the next time I might want to choose a different set of criteria.
I have a form with two date fields: "Initiation_date", and "Correction_date". There is a third field called "Duration". I would like to store the values of all three fields in the corresponding table. "Duration" (Long Integer) would be the number of days from "Initiation_Date" to "Correction_Date" if Correction date is there, or to Date() if Correction date is Null.
I can use an unbound text box to get "Duration_cal" using the following as a control source:
But I cannot get that value (No.of Days) in to the "Duration" field. The reason I want to have "Duration" stored as a number is that it is being used in a query for another calculation (total days used for selected records).
I would like to count the number of working days between two dates, NOT the calendar days, if the workers only work Monday thru Thursday. I know we could use the DateDiff function, but HOW do I count excluding Fridays, Saturdays, Sundays?
I am trying to carryout working days between two dates (Excluding weekends Friday & Saturday) but unable to fix it correctly, However i did search a lot over internet also about built in function but all is showing i have to add it module or macro etc.So, i select the module for Access 2010 but also not finish with function.Table name is "LeaveSettlement" and column name is "Total_Wdays", what field type i have to select for result column.
Public Function LeaveSettlement(ByRef Leave_Start As Date, _ ByRef Leave_End As Date _ ) As Integer ' Returns the number of weekdays in the period from Leave_Start ' to Leave_End inclusive. Returns -1 if an error occurs. ' If your weekend days do not include Saturday and Friday and ' do not total two per week in number, this function will ' require modification.
I'm trying to create a sub to count how many days between 2 dates excluding Holiday and weekend. Using the DateDiff() function is not allowing me to exclude certain days.
I have a problem in calculating the difference between two dates and displaying the output into Years Months Weeks Days. My problem is that dividing the number of days by 30 and requesting an integer is not accurate enough. I have looked at Pat and Jons examples shown in these threads
which either method would suit me as the accurate answer is what I am after.
My problem is that not all of my records would have a start and end date. Therefore both examples would result in an error.
Can anyone please give a hint on how to perform the calculations on those fields which have dates recording the results but ignoring those fileds which do not have a start / end date.
I am having a bad day and I'm sure the answer is so easy that I am going to kick myself but having played around with the modules by limited knowledge is not enough.
What I have is two fields, one is a simple date and the other is slightly more complex as it holds a date but in a different structure (a dated case number).
The case numbers are for example, 150211551223 the date being the first 6 numbers and equaling to 11/02/2015. so the code will need to grab this data, spin it around and convert it.
The formula will then be:
simpledate - convertedcasenumberdate = days between.
(simpledate will always be the latest date of the two).
My database keeps track of training for employees, some of which expires after a period of time, which is in the tables. I need to create a query that displays only the employees and the training that expires during the next 30 days. I have a query that displays the expiration date (this field uses DateAdd and adds the expiration term to the date the employee completed the training) I am trying to add a criteria to this field. I found <=Date()+30 in my searches but that displays all of the records from 12/14 and back. I have tried all kinds of versions of this (obviously, not the correct one) and either get all records or none. (Yes there are records in the database that fall within the the period I am trying to display - that is something that I have been known to forget)
Is it because I am using criteria in a field that is based on DateAdd or what would be the correct criteria for this?
I have 2 dates that I need to count between. Easy enough just use the datediff right? Nope cause it won't count just the 5 workdays. I researched and found that the "w" in the function doesn't work the way I need it to. I found lots of code to make a module that will do it for me and they all include having a holiday table. Right now I don't need a holiday table I just want the simple dates in between.
I have a query that records a status update, and the date it was made by an employee etc. The table has a secondary key related to ... lets say a project table.
E.g. Status Id; EmployeeID;ProjectsID;Status;Date
I want to calculate the average amount of days it takes for a status change occur.
Find the difference between two dates is simple if you're simply looking for the number of days between them. However, if you're looking to express the difference in a bit more user-friendly way, you can use the following code to calculate the difference in years, months, and days. The code accounts for zero values, plurals and the Oxford comma. Further, it automatically sets the later of the two dates to the End date, so the dates can be used interchangeably.
Examples: June 4, 2010, July 3, 2012 returns "2 Years and 29 Days" June 4, 2010, July 5, 2011 returns "1 Year, 1 Month and 1 Day" June 4, 2010, June 5, 2010 returns "1 Day"
Code: Function DiffOfTwoDates(dtmDate1 As Date, dtmDate2 As Date) As String ' Written by Will Knapp, Freelance Access Developer, 2013 Dim dtmStart As Date, dtmEnd As Date Dim strDiff As String ' Resulting String Dim yDiff As Integer ' Year Difference Dim mDiff As Integer ' Month Difference Dim dDiff As Integer ' Day Difference Dim CommaLoc As Integer
How can I calculate the difference between two dates but I only want to count the work days? So if was today and I wanted to go until 6/15/2015 the difference would be 5 and not 7 because I do not want to count Saturday or Sunday. Is there a special %datediff function where I would only count work days?
I am using Access 2013.I am trying to create a query that will count the days difference between two dates. The dates are in the same field. I want to group by Region.So:
tblRegion = RegionID tblStatus = StatusDate
I know how to use the DateDiff when it is two different fields, but I can't figure out how to do it from the same field.
It would only apply the formatting for dates that were equal to the date and +5 days.
I then tried Between Now() and Now() + 14
Same results
I then tried Between Date() and DateAdd("d",14,Date())
No change
I checked the property for the box and the back style is normal.
I am making the back color a light red. I tried to change the fore color red. Nothing.
I displayed what Date() was giving me in a text box control and I displayed what Date() + 14 was giving me in a text box control. They both were showing the correct dates, but my date, which was in between them, was not changing colors.