Configure Integration Services On A Cluster
Nov 18, 2006
Hi
I am having an active/active cluster setup where there are 2 virtual SQL Servers one with default instance and other with named instance.
1) i need to know how to cluster integration service.
2) how are the integration packages are run, are they run by the integration
services service, or by the SQL Instance???
3) When fail over happens from one node to other will my packages continue to run??
i had setup Integration Services on a Cluster per the following article: http://msdn2.microsoft.com/en-us/library/ms345193.aspx.... but
when i do fail over or move the group to another node
... getting an error indicating:
An error occured attempting to read properties for the 'xxx IntegrationServices' resource.
The object already exists.
Error ID: 5010 (00001392)
Do you want to ignore this error and continue
[yes] [yes to all] [no] ...
I understand that integration service can be clustered only once.....
Should i do the clustering in Integration Services in a different Group
than sql server groups??....but then again i wont be able to acces MSDB...
Please provide advice on the matter,,,,,i am desparately waiting for a solution
Thanks in advance....
I
View 5 Replies
ADVERTISEMENT
Dec 17, 2007
Hi
We have this scenario - configured SQL 2005 Cluster on two nodes.
Can we install SQL Server Integration Services on both nodes without Clustering Integration Services?
Will Integration Services works properly?Integration Services service will be started only on one of the nodes.
Best Regards Krasi
View 3 Replies
View Related
Aug 24, 2006
Does anyone know how to install SQL 2005 integration services on a cluster machine?
I have an a-a cluster machine. Both nodes are using SQL 2005 naming instance. During the SQL installation, I did include integration services option as one of my setup items. The setup process was running fine but I can€™t connect to integration services via MS SQL Server management studio. I see below errors:
€śInvalid server name "TESTServerB123". SSIS service does not support multi-instance, use just server name instead of "server nameinstance".
Looks like I must use default instance for 2005 integration services. I re-ran the setup program and added a default instance on the same cluster node. (On that node I have one default instance and one naming instance). Now I can connect to the default SQL Server but when I click on €śstored packages€?, I don€™t see file system and MSDB. It shows nothing at all. Any idea how to make integration services running on a cluster machine?
Thanks
View 5 Replies
View Related
Sep 15, 2015
I am doing some ssis package development in my local machine. I have a requirement to send email the output.
I am developing in my local machine. Is it possible to configure SMTP configuration in my local system to receive the email in Gmail?
if yes, what all are the steps to be followed.
View 3 Replies
View Related
Mar 21, 2007
Hello,
I'm trying to set up SharePoint Integration for our report server. The setup we have is: 1. SQL server hosting the SharePoint databases and the Reporting Server, 2. SharePoint web front end hosting all SharePoint services. I've installed the reporting services SP2 on the SQL server and the reporting services add-in on the SharePoint server.
I configured the report server following the directions here: http://download.microsoft.com/download/f/d/c/fdcb3a53-0cb1-4e67-a1b6-45b89b3c59cf/readme_rsaddin.htm and here: http://www.sharepointblogs.com/helloitsliam/archive/2007/02/21/19801.aspx
Everything seems to be set up correctly, but when I open the Reporting Services Configuration Manager, the SharePoint Integration option shows the error, "The report server cannot access setting in the SharePoint configuration database. Most likely, the Windows SharePoint Services object model...."
I do have WSS 3.0 installed on the report server.
When I look in the logs on the report server it says the login failed for the account I have set as the Windows Service Identity however, when I look at the logs on the SharePoint server it shows that it is granting the account read and write access to each of the SPWebApplications I have set up.
Any suggestions?
Thanks,
Cynthia
View 4 Replies
View Related
Jan 12, 2007
HI,
I am having SQL Server 2005 express edition, how can i configure report services
View 3 Replies
View Related
Aug 15, 2006
While using aspnet_regsql.exe to configure SQL Server for application services, the following error pops up: Failed to query a list of databases names from the SQLserver. Cannot initilaize SSPI package". The page is "Select the Server and Database". Please advise. Thanks.
View 1 Replies
View Related
Sep 11, 2007
Hello friends.
I managed to design an Integration service package,but the desired level of performance has not been achieved(i.e it is performing slow).
So I want to know what are the best practices for optimized solution .
In my package I'm exreacting data from XML file and Storing it in SQL server database with some processing dring data flow.
I'm using
1) Two Script Task Control -In these control,I m opening the connection to XML file through VB.net code and
iterating each record at a time.
2)Two OLE DB Command -Each fetched record from script task component is processed in OLEDB command through
stored procedure and then inseted into database.
3)One for Loop -This loop contains two script Task control and two OLEDB Command control,
(mentioned above),for fetching single record and inserting it in database.
4)One derived Column
5)One Multicast
6)One Character Map
7)One OlEDB Source
As with my current performance I'm able to insert one record in every .5 second (Which is much below to acceptable limits)
Is control lying disabled on SSIS designer pane also affect the performance of execution.
View 4 Replies
View Related
Jan 10, 2007
I am trying to configure a reporting server on my laptop at work. This laptop is running Vista and IIS 7. When I install reporting services, the option for "Install the default configuration" is disabled (greyed out) during setup. The install is successful, but then when I try to connect in the Reporting Services Configuration Manager, I get an unhandled exception ("A WMI error has occurred an no additional error information is available."). If I continue, this error continues to crop up as I attempt to configure the Report Server. When I attempt to configure the virtual directory, the configuration manager crashes. Then, when I navigate to the reportserver page, I get a page that states:
Server Application Unavailable
The web application you are attempting to access on this web server is currently unavailable. Please hit the "Refresh" button in your web browser to retry your request.
Administrator Note: An error message detailing the cause of this specific request failure can be found in the application event log of the web server. Please review this log entry to discover what caused this error to occur.
Any ideas for a solution or workaround would be greatly appreciated.
Thanks,
Dave
View 1 Replies
View Related
May 16, 2008
I've created a SSIS package with a DataReaderDestination and a SSRS report that points to it.
I referenced these links during development and I have everything working as expected locally. **I changed the config files as stated on both my local machine and our server. My config matches the example exactly.
http://msdn.microsoft.com/en-us/library/ms345250.aspx
http://msdn.microsoft.com/en-us/library/ms159215.aspx
When I attempt to deploy my report project to the server I get this error message:
"An attempt has been made to use a data extension 'SSIS' that is not registered for this report server."
In the report manager data source properties page it reads:
"The data processing extension used for this report is not available. It has either been uninstalled, or it is not configured correctly."
In SQL Server Management Studio data source properties page SSIS is not a data source type option.
I've tried restarting both the Reporting Services and Integration Services on the server to no avail.
Any suggests? My problem is I can't get the SSIS to be recognized source on the server.
View 1 Replies
View Related
Jun 12, 2015
We have 15-20 report server environments including Dev/SIT/UAT/PROD/DR etc. so instead of configuring it on each servers, we would like a script to use with parameters.
After installing the SSRS 2012 package on each server with given instance and service account, I would like to configure the SSRS through script instead on running the Configuration manager RSConfigTool.exe manually.
we already have created the database beforehand using the scripts provided by WMI. do we need db_owner permission on msdb and master database to configure SSRS?
View 2 Replies
View Related
Aug 22, 2007
I have a report created using MS SQL Server 2005 reporting services and deployed to the report server. I added a subscription for the report to be scheduled to run and emailed to someone on a regular basis. But now we want the report emailed ONLY when there is data returned. If no data is returned after the report runs then don't email it.
Does anyone know how to do that?
Thanks!
View 10 Replies
View Related
Apr 21, 2008
Hi,
I have a Windows 2008 server 64-bit SP1 and I have installed SQL 2005 SP2 Enterprise Edition 64-bit. My current version is 9.00.3042.00. I am trying to configure Reporting Services and I am having lots of trouble getting the Application Pools to work properly. I have followed the Microsoft Technet paper 839480 "How to Install and Configure Reporting Services on Windows Server 2008". In the "Configure Reporting Services" part, I have successfully configured everything (all arrows are green) and have the following setup:
Report Server Virtual dir: ReportServer Default Web Site
Report Manager Virtual dir: Reports Defualt Web Site
Windows Service Identity: ReportServer with a service acct login
Web Service Identity:
Report Server: ReportServer,
Report Manager: DefaultAppPool (I get an error when I try to configure it to anything else: ReportServicesConfigUI.WMIProvider.WMIProviderException: An unknown error has occurred in the WMI Provider. Error Code 800708AC at ReportServicesConfigUI.WMIProvider.RSReportServerAdmin.SetWebServiceIdentity(String applicationPool)
The one thing I notice in the SQL Server configuration manager is that there is a red dot next to the SQL Reporting Services services even though the green arrow is there to show it is running.
When I look in IIS7, I see the application pools Reports and ReportServer and they are both in Integrated mode. When I try to go to http://localhost/reportserver, it gives an error. It will work if I change both application pools to classic. But then when I try to go to http://localhost/reports, I get an error:
"REQUEST IS NOT AVAILABLE IN THIS CONTEXT".
I have read up on IIS7 and it says that:
"This error is due to a design change in the IIS7 Integrated pipeline that makes the request context unavailable in Application_Start event. When using the Classic mode (the only mode when running on previous versions of IIS), the request context used to be available, even though the Application_Start event has always been intended as a global and request-agnostic event in the application lifetime."
So, how do I configure these application pools to work using IIS7 with SQL 2005 Reporting Services on a Windows 2008 server? I have tried all kinds of different things based on what I am reading on the net and nothing is working. Anybody have any suggestions?
Thanks!
Isabelle
View 3 Replies
View Related
Mar 23, 2007
Hi,
I have just install SQL 2005 SP2 and trying to get Window SharePoint Services V3 integrated with SQL 2005 SP2 reporting services.
In SharePoint Central Administration, I select the Reporting Services Integration page and have setup the Report Server Web Service URL and Authentication Mode. I then goto Grant database access, specify the SQL server name, get promted for a username and password that has access SQL Reportserver and get the following error "The group name could not be found"
Does anyone have any ideas?
Thanks
View 5 Replies
View Related
Oct 11, 2007
Hello, I have a problem when trying to fully process an SSAS database using Integration Services "Analysis Services Processing Task" task. I have 2 of these tasks which are responsible for processing the Dimensions then the Cubes. When I run the package either via the BIDS environment or on the local server from the Integration Services engine, I will get an error after about 20 minutes stating:
"Error: Memory Error: Allocation failure. Not enough storage is available to process this command""Error: Errors in the metadata manager. An error occurred when loading the <cube name> cube from the file \?D:Program FilesMicrosoft SQL ServerMSSQL.2OLAPDataMyWarehouse<cube file>.xml"
The cube name is not specific, it will fail and any of my cubes could be in the error log
If I fully process the AS database using the AS engine (logon to local AS server, right-click AS database and click Process), I get no errors at all, it processes and completes fine. The processing options are identical when I run in AS or via the SSIS "Analysis Services Processing Task" task.
I've searched quite a lot online but no joy, the information I have gleaned from various sites does not directly link SSIS with SSAS processing problems.
When either the AS processing starts via SSAS or SSIS the memory usage of MSMDSRV.exe increases to around 1.4 / 1.5 GB but never goes to 2GB ever, even when the error appears.
I've done the following with no effect.
" Have run via AS and works fine
" No specific cube it fails on
" Have created a Dimension only package, same problem
" Changed the maxmemorylimit
" Changed the connections to localhost
" Memory DOES NOT max out on server
Server Specs:
Windows Server 2003 Standard + Service Pack 2
4GM ram, 2GB paging file
SQL Server 2005 + Service Pack 2
Can anyone help?
Andy
View 2 Replies
View Related
Jun 10, 2007
Can anyone help me with a problem I have with SSRS 2005? How do I configure SQL Server 2005 Reporting Services to deliver subscription e-mails to addresses external to my windows domain?
I've been having trouble configuring the Report Server e-mail delivery component to send subscription e-mails to addresses outside the domain on which the report server is hosted.
For e.g. since my local windows domain is named "smartsystems.com", I have found that the Report Manager does not have any problems sending subscription mails to "eawagu@smartsystems.com" but throws up an error whenever I include "eawagu@yahoo.com" in the recipients' list.
Any insights?
View 1 Replies
View Related
Jan 8, 2007
We have set up SQL Server 2005 failover cluster with 2 nodes, on Windows 2003. I'm now trying to add Reporting Services. I don't see any documentation for how to do this. Is it similar to adding Analysis Services? If I use this command I'm not sure what to put in several paramaters:
start /wait c:<path-to-setup>setup.exe /qn VS=<my-virtual-server-name> INSTALL=RS_Server INSTANCENAME=MSSQLSERVER ADDLOCAL=RS_Server ADDNODE=n GROUP="Cluster Group" IP="111.11.11.11,<my-virtual-server-name" ADMINPASSWORD=xxxx SAPWD=xxxx INSTALLSQLDIR=c INSTALLSQLDATADIR=c RSACCOUNT=mmmxxxxx RSPASSWORD=<domain-user-psswd> SQLBROWSERACCOUNT=<mmmxxxxx> SQLBROWSERPASSWORD=<domain-user-psswd> SQLREPORTING=1
My question are for:
IP: do i just put the virtual ip and name here, or every ip in the node?
INSTALLSQLDIR: is c drive correct here, or what is this?
INSTALLSQLDATADIR: is c drive correct here, or what is this?
RSACCOUNT: is this correct, not in the example in document ms144259 and what should go here?
RSPASSWORD: same as above
SQLBROWSERACCOUNT: what goes here?
SQLBROWSERPASSWORD: same as above
Thanks so much for any help.
View 4 Replies
View Related
Jun 3, 2008
Hi,
I've a problem with my failover cluster. It's a two node cluster and if the active node fails, the second one overtake the database and everything is fine. But only the reporting service doesn't start on the second node. The service is off. All other ones are starting correctly. Is there to configure something special to the Reporting Services?
Regards
Sascha
View 3 Replies
View Related
May 30, 2006
I'm having a world of trouble with the Reporting Services Server. The install went fine. I went in to configure the Report Server and when creating the Report Server and the Report Manager virtual directories I get the following error: "The virtual directory could not be created. The previously set virtual directory will still be used." The problem with this is that I have not previously set a virtual directory. When clicking on the link I get the additional error information: "System.IO.FileNotFoundException:
at System.Runtime.InteropServices.Marshal.ThrowExceptionForHRInternal(Int32 errorCode, IntPtr errorInfo)
at System.Management.ManagementObject.InvokeMethod(String methodName, ManagementBaseObject inParameters, InvokeMethodOptions options)
at ReportServicesConfigUI.WMIProvider.RSReportServerAdmin.CreateVirtualDirectory(String virtualDirectory, String path)"
When I check IIS the directories were created but the Reporting Services Configuration Manager does not see them unless I attempt to recreate them again without deleting them from IIS.
Anyone have any ideas as to this disconnect?
Thanks in advance!
View 11 Replies
View Related
Apr 18, 2007
Does anybody know of a notification services using SSIS? Is it SendMail or otherwise? Is there a step-by-step practice on how to create one?
View 19 Replies
View Related
Dec 3, 2007
Hey,
I have a 3 node cluster running 6 instances of SQL Server, I want to install Analysis Services along side of one of the SQL 2005 instances. Thus one of the cluster instances would host SQL Server DB, Analysis Services and SQL Agent. Is this possible or does Analysis Services need it's own Cluster Instance.
Thanks!
View 3 Replies
View Related
Jun 16, 2015
if it is supported to install Reporting Services on both the active and passive nodes in an SQL Server Failover Cluster and use the non-active node as a warm standby?We have relatively simple reporting requirements so the idea would be that if Node 1 went down, we could just repoint our users are Node 2 temporarily. Both reporting services instances would be configured to target the same SSRS database running on the SQL Cluster.
View 2 Replies
View Related
Sep 30, 2015
So the cluster install forced us to install Full-Text on our cluster (which we don't want to use, but I guess we don't have a choice about installing it). Now I'm going through to update the services from Manual to Automatic (on the appropriate nodes) and I see SQL Full-text Filter Daemon Launcher running.
What is the harm in turning it off if we're not using Full-Text capabilities?
View 2 Replies
View Related
May 24, 2007
Is there a way to give customers access to SSIS? They need to be able to create their own SSIS packages. Of course we have more then one customer so it would be nice to have modular security in place where they don't get to see customers abc and customer xyz packages. Only their own.
thanks!
View 6 Replies
View Related
May 8, 2008
Hi All,
I have created an integration services project (attached is a screenshot) that workes against the flat file (.DAT extension) and it does some manipluation in the data and then load it into the table. Everything works fine.
Now I want to get the name of my flat file source fille (which is a .DAT file) and then insert it in the table.
I am running th integration services against different .DAT files (only one file at one time) which are located on different locations.....so what I want is that, whenever I run the package it do the usuall processing and then while loading the data in to the destination table, it also load the name of the file into the destination table (lets called a field "FileName" of nvarchar type in the table "Comphistory")
How can I achieve this?
I am looking for a quick and easy help.
Thanks,
Zee
View 4 Replies
View Related
Jul 25, 2007
Problem
When you have a SSIS package that contains a connection from a data source, this connection is not updated when the data source changes based on a configuration change.
Situation :
A SSIS solution contains 3 configurations : Development, Test, Production. You can create those configurations in configuration manager of the solution.
The SSIS project contains one Data source. It doesn't really matter what type but I take SQL Server. The database server in development is SQL_DEV, in test is SQL_TEST and in production is SQL_PROD. Initially they are for all configurations the same. You can specify those values by changing the active configuration and then editing the Data source.
In the SSIS package (DTSX), you can create a connection manager based on a Data source.
If you change the Data source, the connection manager is also changed. If you change the Data source by changing the active configuration, the connection manager is not being updated.
If you think this isn't a big issue think big. We have 4 configuration, 10 shared Data sources and 25 DTSX packages. That would give a maximum of 1000 settings (4 x 10 x 25). Using this method it can be reduced to 40 (4 x 10). Of course this is a theoretical but it is very common to have the destination data source re-used on all packages, which still would be 100 settings (4 x 25)
Steps to reproduce
- create a new SSIS project
- In the solution explorer, create a new Data source named TestSource.
- In the connection managers window of Package.dtsx, create a new connection from a Data source.
- Make some changes in to TestSource.ds under the Data Sources. For example change the server or the database.
- Verify that those changes are also in the package.
- in the solution explorer, right click the solution and select configuration manager
- under active solution configuration, create a new configuration named test.
- Set the copy settings from : development
- Verify that Create new project configuration is checked.
- click OK and close.
- Notice that the active configuration is now Test
- Make some changes the Testsource.ds like a different server.
- Verify that those changes are also in the package.
- Make the development configuration as active.
- Notice that the Testsource.ds contains now the original settings.
- You will notice that the connection manager still contains the "test" settings and not the development settings.
- If you create a deployment utility it will still contains the wrong values.
with regards,
Constantijn Enders
View 1 Replies
View Related
Jun 16, 2006
Hi all,
Can someone explain to me why I am getting this kind of error though I am able to integrate all the data succeesfully to the next destination.
Ronald
SSIS package "Prescription.dtsx" starting.
Information: 0x4004300A at Data Flow Task, DTS.Pipeline: Validation phase is beginning.
Information: 0x4004300A at Data Flow Task, DTS.Pipeline: Validation phase is beginning.
Information: 0x40043006 at Data Flow Task, DTS.Pipeline: Prepare for Execute phase is beginning.
Information: 0x40043007 at Data Flow Task, DTS.Pipeline: Pre-Execute phase is beginning.
Information: 0x4004300C at Data Flow Task, DTS.Pipeline: Execute phase is beginning.
Error: 0xC0202009 at Data Flow Task, SQL Server Destination [521]: An OLE DB error has occurred. Error code: 0x80040E14.
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 58, column 1. The destination column (PatientId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 27, column 12. The destination column (ServiceId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 26, column 12. The destination column (ServiceId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 25, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 24, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 23, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 22, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 21, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 20, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
Information: 0x40043008 at Data Flow Task, DTS.Pipeline: Post Execute phase is beginning.
Information: 0x40043009 at Data Flow Task, DTS.Pipeline: Cleanup phase is beginning.
View 3 Replies
View Related
Apr 25, 2006
Hi,
is Integration Services included in SQL Server Express?
In what version/module?
Thanks
just Do It
View 1 Replies
View Related
Jun 16, 2006
Hi all,
Can someone explain to me why I am getting this kind of error though I am able to integrate all the data succeesfully to the next destination.
I am trying to get the Prescription table from Access to SQL SERVER 2005 database
Ronald
SSIS package "Prescription.dtsx" starting.
Information: 0x4004300A at Data Flow Task, DTS.Pipeline: Validation phase is beginning.
Information: 0x4004300A at Data Flow Task, DTS.Pipeline: Validation phase is beginning.
Information: 0x40043006 at Data Flow Task, DTS.Pipeline: Prepare for Execute phase is beginning.
Information: 0x40043007 at Data Flow Task, DTS.Pipeline: Pre-Execute phase is beginning.
Information: 0x4004300C at Data Flow Task, DTS.Pipeline: Execute phase is beginning.
Error: 0xC0202009 at Data Flow Task, SQL Server Destination [521]: An OLE DB error has occurred. Error code: 0x80040E14.
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 58, column 1. The destination column (PatientId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 27, column 12. The destination column (ServiceId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 26, column 12. The destination column (ServiceId) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 25, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 24, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 23, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 22, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 21, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
An OLE DB record is available. Source: "Microsoft SQL Native Client" Hresult: 0x80040E14 Description: "The bulk load failed. Unexpected NULL value in data file row 20, column 7. The destination column (AllergyCode) is defined as NOT NULL.".
Information: 0x40043008 at Data Flow Task, DTS.Pipeline: Post Execute phase is beginning.
Information: 0x40043009 at Data Flow Task, DTS.Pipeline: Cleanup phase is beginning.
View 1 Replies
View Related
Jun 20, 2006
I'm trying to use the new integration services and have found all kinds of help for it, but where is it? I can't find it. Is it in the SQL Server Management Studio?
View 1 Replies
View Related
Jul 25, 2007
Hi,
I want to insert datas from a txt-file into a sql-table.
Therefor i would use a xml-file for the structure!
How can i refer this xml-file to a measurement insertion task?
Tanks for your help and sorry for my bad english :rolleyes:
View 1 Replies
View Related
Jul 23, 2005
I am trying to know how to read many XML files within one data flowtask. I have many many files that I would like to apply to with thesame data flow so I need to know how to read them in and what taskshould I use under SQL 2005 DTS/Integration services.Thanks for your help!JON
View 1 Replies
View Related
Jan 14, 2008
Good morning,
I've to do a mining project and I intend to use the SSIS.
I've done a clustering plugin last year on analysis services and I also want to use it.
Let me try to explain the architecture of the process:
1) Receive data (read data from the database - these data are texts, actually)
2) Pre-process the data (transform the texts in a sparse matrix) using a new plugin
3) Call my clustering plugin and assign it to read the table created on the previous step
4) Call my KNN plugin to classify other pre-processed texts using the clusters found on the previous step as classes.
5) Show results.
Alright... It all running as a workflow on integration services
Here are my doubts:
A) How to view and use my plugin made for Analysis Services on Integration Services ? (is it possible or will I have to create another plugins from zero just to run on Integration Services ?)
B) Assuming the previous step is possible, how to modify my plugins to define inputs and outputs to do the correct communications between each plugin ? I think this is the most important question. Is it simple to do ? Is there any documented examples ?
Thanks a lot for your attention once more,
-Renan Souza
View 1 Replies
View Related