DTS: One Failure Step For Multiple Process Steps

Dec 17, 2004

How can I make this work?

I have two process steps in a package and one failure step. Both process steps have On Failure workflows to the failure step. The problem I'm having is that it seems if two or more workflows go to the same failure step then neither go to the failure step, but it does go if only one process step is attached to it.

I know I can create duplicate steps for each process step, but I was hoping to be able to do it this way FMI.

Thanks for your assistance.

View 1 Replies


ADVERTISEMENT

Is It Possible To Skip All Steps Following The Script Task Results (Step 1) In A For Each Container?

Jun 13, 2006

Is it possible to skip all steps following the script task results (Step 1) in a For Each container. I am iterating thru all the files in a For Each container and parsing a few lines of the file and based on the result I want to force the For Each loop to get to the next file instead of executing the next steps. Is it possible to force the for each loop to get the to the next file if the test criteria in the very first step (Script Task) fails. Any inputs will be much appreciated.



THanks,

MShah

View 1 Replies View Related

Failure Notifications For Individual Steps?

Apr 18, 2008

Good day,

I have a Job that runs every half an hour, and has about 30 steps. If a step fails it moves on to the next step (the steps are not dependant on one another)... However I would like to receive notification if that occurs. I have SQL 2005, with database mail enabled and set up (works fine for other jobs)... The question is how do I get it to send me an email if a single step fails, however the job on a whole succeeds?

Do I need to set up a step between each job?

Step 1 An actual step, on failure: step 2 On success Step3
Step 2 A step that emails the failure of step 1, then goes to step 3
Step 3 An actual step

etc etc... Or is there a better way?

View 1 Replies View Related

How Do You Add A Job(multiple Steps) To Be One Of The Steps Of Another Job

Jun 6, 2001

Hi,
I have two job J1 and J2, each one has 10 steps. Now I want J2 to be the 11th step of J1 and I did not want manually type all the steps of J2 to be 11-20 step of J2. Is there an easy way through TSQL to do this ?
sp_add_jobstep only works when the step is OS command or a script but not a job

View 2 Replies View Related

The Process Could Not Be Created For Step 1 Of Job

Jun 11, 2008

Hi I am facing an issue running an SSIS package on a SQL Server 2005 SP2 machine



Here's more information:



1) The SSIS package that dumps data returned from a stored procedure call to an excel (CSV) file. The package owner is a SQL Login called AppAdmin. The login has user memberships/roles in two databases:



1.1) Database AppDB - Has execute and select permissions.

1.2) Database msdb - SQLAgentUser role



The package has one step that is run as a SSIS Proxy account PrxApp. The Proxy is based on a credential CrdApp which is based on a windows account <domain>AppAccount. This account is part of the Local Administrators group and also has SA rights in on the server. The same account is also used to run all the SQL Server Services on this machine. The machine is part of a 2-node cluster (A/P).



When I try to execute this package (as a schedule or one-off), I am getting the error mentioned in the Subject. I have checked a few posts using google and have acted upon as many suggestions that I possibly could (e.g. change this, change that...did not do any registry modification, etc). Many of these posts have been talking about changing local security policy and adding the user to several groups. Did that, but still does not work in a SQL Agent Job.



The account currently has the following rights (local security policy)



Act as part of OS
Perf. volume maint tasks
Lock pages in memory
Replace process level token


One thing that I did notice and don't know if that affects the issue is that the following groups (and SQL Logins) are missing from my Windows groups listing (Computer ManagementUsers and GroupsGroups). Note that this is a Windows 2003 machine.



(a) SQLServer2005MSSQLUser$<machine_name>

(b) SQLServer2005SQLAgentUser$<machine_name>



Now these groups (and logins in SQL Server) do exist on some other SQL2005 machines that I have checked to see what could be wrong.



Any help at all is greatly appreciated. If you need any more information please let me know.



Thanks

Shishir Khandekar

View 6 Replies View Related

Actions On SQL Job Step Failure

Feb 26, 2001

Hi Team,

I've recently had a situation where some of the steps in the daily backup job failed. The job is defined such that if a step fails, it goes on to the next step (these are dev. backups :)

Is there a way that I can tell it to notfy me of the step failure AND go on to the next step? The notification is reporting that the job was successful when in fact a couple of the steps failed. Is there any way around this?

Thanks in advance,

View 2 Replies View Related

Dts Job Failure Troubleshooting Step

Dec 19, 2006

I am having one DTS job failed but it has not written much in the history. i wont to know the exact cause of the failure.
please help..

thanks in advance

View 2 Replies View Related

Multiple Steps For Each Query

Jun 12, 2015

My end game is to automate some of my monthly queries in a Job in SQL Server Agent. Right now I have two metric tables. One table is the name and comment with the PK. The secondary table is attributes/detail, such as reporting month, target and actuals.

I am currently running all different types of queries to get the aggregates. I'd like to get these into a job so it would run automatically and update the reporting table.

Would you recommend making one step or multiple steps for each query? I am trying to use an intelligent approach to begin to load the tables.

View 2 Replies View Related

Urgent - Scheduled Job Having Multiple Steps

Dec 17, 2004

Hi,

Previously I was performing the process of populating my DataMart and then processing my cubes via 2 separate job scheduled one after the other and with about 30 minutes idle time in-between (just in case).

I now have tried to make a single job with both of the above as 2 steps (one after the other) of a single job.

However when I was done, I did a right click and tried to run the newly created job but instead of what I was hoping (that the job would start, would perform the 1st step, followed by the 2nd), it instead popped up a dialog box asking (I think) which step needs to be executed :(

Is there a solution so that when the job is scheduled to run, it should start performing the steps in the order rather than waiting for someone to select which step to perform.

Will really appreciate urgent reply.

View 2 Replies View Related

Urgent - Scheduled Job Having Multiple Steps

Dec 17, 2004

Hi,

Previously I was performing the process of populating my DataMart and then processing my cubes via 2 separate job scheduled one after the other and with about 30 minutes idle time in-between (just in case).

I now have tried to make a single job with both of the above as 2 steps (one after the other) of a single job.

However when I was done, I did a right click and tried to run the newly created job but instead of what I was hoping (that the job would start, would perform the 1st step, followed by the 2nd), it instead popped up a dialog box asking (I think) which step needs to be executed :(

Is there a solution so that when the job is scheduled to run, it should start performing the steps in the order rather than waiting for someone to select which step to perform.

Will really appreciate urgent reply.

View 2 Replies View Related

Failure In Starting The Process For The User Instance

Apr 13, 2006

High everybody,

I have a set of winforms (.NET 2.0 assemblies) ( 6 total ) that each tries to open a connection to the same Database file using the same connection string. In the connection string, UserInstance is set to true.

If each winform is started manually after opening the session on the computer, the connection to the database performs well for every winform.

If the same winforms are automatically started at the opening of the user session, the the following error is reported by each application when trying to open the connection :

Failed to generate a user instance of SQL Server due to a failure in starting the process for the user instance. The connection will be closed.

The only way to overcome this problem is :

to stop the winforms, to stop the SQLExpress service, to kill the remaining sqlserv.exe running task, then restarting SQLExpress service, and finally manualy start the winforms.

Any help would be greatly appreciated.



View 11 Replies View Related

SQL 2012 :: Failure In Starting Process For User Instance

Jul 23, 2014

I am trying to use SQL Server 2012 for the first time. I am running Win 8.1. I create a local website and sample webpage using Visual Studio 2012 for Web. Running this page on my localhost, when it attempts to create a new SQL database this exception is thrown:

"Failed to generate a user instance of SQL Server due to a failure in starting the process for the user instance. The connection will be closed."

View 1 Replies View Related

Log Shipping Failure Sqlmaint.exe Failed. [SQLSTATE 42000] (Error 22029). The Step Failed.

Sep 13, 2001

I have log shipping set up between 2 SQL 2000 SP1 Servers on Win 2000. The db is small 10 meg, and when the restore job on the backup server fails I am getting "sqlmaint.exe failed. [SQLSTATE 42000] (Error 22029). The step failed." as the message, the maint paln on the primary server show no error. Anyone seen this before? The restore has worked 3 out of 5 times

View 2 Replies View Related

Multiple Step OLE DB Error From VB

Mar 29, 2004

One of our users is getting this error message.

Microsoft OLE DB Provider for ODBC Drivers (0x80040E21) Multiple-step OLE DB operation
generated errors. Check each OLE DB status value, if available. No work was done.

This is the only user that is currently getting the message. Last week another user got this one day and then it stopped.


Inside VB6 code, we're sending some filters to an ASP that in turn sends a SELECT based on those parameters the SQL database and we get data back to the program.


Stepped through the code and found the error returns after this line

oSqlServConn.Open "Provider=MSDAOSP;Data Source=MSXML2.DSOControl.2.6"



Any thoughts out in ForumLand? Please take it easy on me since I didn't write most of this code. Just trying to solve the problem. :)

View 6 Replies View Related

Multiple-step Ole Db Error

Mar 21, 2006

When trying to connect to sqlexpress, I get the rather uninformative error message:

Error No. -2147217887
Multiple-step OLE DB operation generated errors. Check each OLD DB status value, if available. No work was done.

Here's the connection string I'm using:

strDbConn = "Data Source=.SQLEXPRESS;AttachDbFilename=" & _
DbPath & ";Database=rawtf_1;Integrated Security=True;User Instance=True; " & _
"Trusted_Connection=Yes;providerName=System.Data.SqlClient"


What can I do correct this problem?

View 18 Replies View Related

Multiple Step OLEDB Error

Apr 2, 2007

The error message is

-2147217887 - Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.



View 1 Replies View Related

Multiple-step OLE DB Operation Generated Errors

Jan 31, 2005

Hi!
We have installed MPS for Service Provisioning on domain controller. SQL 200 is also installed on this server. EventView logs per 15 second following error:

Source: Provisioning and Audit Recovery Service
Category: None
Event ID: 5896

"Error occurred while moving records to the audit log database. SQL server reported errors:
Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.

For more information, see Help and Support Center at http://go.microsoft.com/fwlink/events.asp."

I did not find the problem source and the solution.
Any idea?

Best Regards
Cicek

View 1 Replies View Related

Multiple-step OLE DB Operation Generated Errors

May 16, 2006

Hello....

I have two linked server... (ServerB and ServerC) which reside on ServerA. I am able to connect to the remote database using "Select" statements without any issues.

When I run this query, It is successful:

delete [SERVERB].MyDatabase.dbo.TableName
from [SERVERB].MyDatabase.dbo.TableName t1
Left join MyDatabase.dbo.TableName t2 on ( t1.ID = t2.ID and
t1.EmployeeNumber = t2.EmployeeNumber and
t1.AccountNumber = t2.AccountNumber)
where t2.ID is null;

However, when I change [SERVERB] to [SERVERC], I receive two errors:

"Could not find server 'ELEARN-FRM-BETA' in sysservers. Execute sp_addlinkedserver to add the server to sysservers."

And

OLE DB provider "SQLNCLI" for linked server "ELEARN-FRM-BETA" returned message "Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.".

When I run profiler on ServerC, I see traffic... mainly a whole bunch of exec "sp_cursorfetch" operations, so I know the connection is valid.

Any ideas?

Forch

View 8 Replies View Related

Multiple-step OLE DB Operation Generated Errors?

Jan 12, 2006

I am trying to use sqlexpress (release version) with vb6. The mdf file is located in a subdirectory of the app.path. When I run the program I get the following message:

Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.


What am I doing wrong? Here's the code:

Dim DbPath As String, strDbConn As String
DbPath = App.Path & "dbs" & DbName
strDbConn = "Data Source=.SQLEXPRESS;AttachDbFilename= " _
  & DbPath & ";Integrated Security=True;User Instance=True"
 
Set DbConn = New Connection
DbConn.connectionString = strDbConn
DbConn.Open

View 3 Replies View Related

Multiple-step OLE DB Operation Generated Errors

Dec 18, 2006

I'm trying to view a report on Report Manager (Reporting Services 2000) that displays Analysis Services (2000) data. I keep getting the following error message:

An error has occurred during report processing. (rsProcessingAborted) Get Online Help

Cannot create a connection to data source 'CubeName'. (rsErrorOpeningConnection) Get Online Help

Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.

I am using Visual Studio 2003 to build the report and I can successfully view the cube and pull data but when I deploy the report and data source to Report Manager I keep getting this error message. I am not using my credentials for the data source I am using a SQL account that is a sys admin and has access to the cube I am trying to view.

Additional Information: Visual Studio - local machine
SQL Server/Analysis Services - Machine A
Reporting Services - Machine B

View 1 Replies View Related

SQL 2012 :: Use SSIS Or Stored Proc Or Combination To Handle Stopping A Process On Failure

Apr 7, 2015

A project I'm working on consists of a Main stored procedure which then runs about 30 nested procedures. The client wants to know when a certain nested SP fails, but wihtout rollbacks, as they may want to fix a data item manually (such as a missing Patient ID, that they have to call someone about). At this point, we don't want to roll back anything but halt the rest of the nested SP's and send out an email to someone that they have to check out a missing PatientID.

I'm wondering if an SSIS package would handle this better than just using a Stored Procedure. When that SP runs, it will also update a "Process tracking" table in the backend, that would update [Lastprocessran] with a number. I'm thinking that if they run the main SP again, after making a manual correction, that they could re-run the main SP, and it would bypass any step that already ran successfully based upon the [Lastprocessrun] number.

View 2 Replies View Related

Multiple-Step Operation Cannot Be Generated Check Each Status Value Error

Jan 22, 2007

Hi All,

I have a field 'Rowguid' of type uniqueidentifier in a table. This field is the last field in the table. In this case if I update a record through the application I don't get any error. Suppose if there are additional fields after the field Rowguid I get the error "Multiple-Step operation cannot be generated Check each status value"

For your reference I have used the following statement to add the RowGuid field

Alter table <tablename>
Add RowGuid uniqueidentifier ROWGUIDCOL NOT NULL Default (newid())

Can anyone please help me.


Thanks

Sathesh

View 3 Replies View Related

Distribution Agent Error - (Multiple-step OLE DB Operation Generated Errors....)

Oct 18, 2005

Hi,

View 5 Replies View Related

Urgent Multiple-step OLE DB Operation Generated Errors. Check Each OLE DB Status Value

Nov 30, 2007

I am using execute sql task and my sql statement contains

EXEC test ?

procedure test has 2 parameters. I added parameters using parametermapping tab. When I run i get an error message


Multiple-step OLE DB operation generated errors. Check each OLE DB status value

View 1 Replies View Related

Multiple-step OLE DB Operation Generated Errors. Adding Colums Using ADOX

Nov 26, 2007

Hi
I'm trying to add columns to an existing table using ADOX. I'm using C++/CLI. My code is as follow

Table->default->Append("new_column", ADOX:: DataTypeEnum::adWChar, 255);
Table->default["prev_instance_id"]->Properties["Jet OLEDB:Compressed UNICODE Strings"]->default = true;

The first line of code works fine but when I try to set the value of the property I get the following excpetion:

An unhandled exception of type 'System.Runtime.InteropServices.COMException' occurred in MyDll.dll
Additional information: Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.

Any idea?

Marco

View 7 Replies View Related

Export From Excel To SQL.. Multiple-step OLE DB Operation Generated Errors. Check Each OLE DB Status Value, If Available.

Nov 9, 2007

Hi all,
We have Windows 2003 64 sp2 Xeon, 2005 EE SP2 64 bit...
Trying to do conversion from DTS sql 2000..One package use load from excel to sql..So I tried to create same thing by myself.. Hell, so many issues.. So I used wizard, package created, I changed Run64bit to False, tried to run package, once - completed in debug mode.. Now it's time to create deployment utility and deploy package..During execution of manifest file got error:

Description: "Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work was done.".

In BIDS, open up solution and tried to rerun package again - no way,".. cannot acquire connection from connection manager blah blah blah.."
Even tried to fire package without debugging, it fires 32 bid execution utility, so no question about 64 bit mode.. package failed..
Execution GUID: {CE11CF95-A25E-4285-A8B0-9E28E51A6785}
Message: ExternalRequest_post: 'IDataInitialize::GetDataSource failed'. The
external request has completed.
Start Time: 2007-11-09 09:41:25
End Time: 2007-11-09 09:41:25
End Log
Error: 2007-11-09 09:41:25.95
Code: 0xC0202009
Source: Package_name loader Connection manager "SourceConnectionExcel"
Description: SSIS Error Code DTS_E_OLEDBERROR. An OLE DB error has occurred.
Error code: 0x80040E21.
An OLE DB record is available. Source: "Microsoft OLE DB Service Components" H
result: 0x80040E21 Description: "Multiple-step OLE DB operation generated error
s. Check each OLE DB status value, if available. No work was done.".
End Error
Log:
Name: OnError

Source Name: Data Flow Task
Source GUID: {2A373E56-8AAF-40E9-B9EF-4B2BB40175F0}
Execution GUID: {CE11CF95-A25E-4285-A8B0-9E28E51A6785}
Message: SSIS Error Code DTS_E_CANNOTACQUIRECONNECTIONFROMCONNECTIONMANAGER
. The AcquireConnection method call to the connection manager "SourceConnection
Excel" failed with error code 0xC0202009. There may be error messages posted be
fore this with more information on why the AcquireConnection method call failed.

Any help..?

View 1 Replies View Related

Sample Files From The Book SQL Server 2005 Reporting Services Step By Step

Jan 18, 2008



Hi All,

Please let me know where can i find the sample files and rs2005sbsDW database in msdn library as i dont have CD provided along with the book.

Please give me the link of the sample files so that i can download it for testing the sample application.

Regards,
Prabhanjana

View 1 Replies View Related

Step By Step SQL2000 Failover Cluster Upgrade To SQL2005

Oct 13, 2006

is there such a paper? if so, can you pls point me to it? thx in advance

View 4 Replies View Related

Step By Step To Publish/deploy The Report Project To The User Pc ?

Oct 3, 2007

hye everyone,

after finished do the report and deploy at IIS/report manager in local pc..

i want to know , what is the step /how to deploy the report project at the user's pc/ client pc /other server..


thanks in advance
thank you very much

View 16 Replies View Related

Reporting Services :: How To Convert RDL File To RDLC Step By Step

Jun 18, 2012

I want to convert .rdl  to .rdc need full steps.Actually i created .rdl report using sp sucessfully.Now i want to convert it to rdlc while doing it iam getting some authentication error and some thing else.I created rdl in 2008 and i want to change it to rdlc 2010.

View 5 Replies View Related

Execute Package Results Different To Step By Step Execution - Uses Raw File

Jan 31, 2007

I have a package that has multiple data flow tasks. At the end of a task, key data is written into a raw file (file name stored in a variable) that is used as a data source for the next task. Each task requires a success from the preceding task.

Here's the rub:

If I execute the entire package, the results of the package (number of records of certain tasks) differs significantly from when I execute each step in the package in turn (many more records e.g. 5 vs 350).

I get the feeling that the Raw file is read into memory before it is flushed by the previous task, or that the next task begins preparation tasks too early.

Any help is greatly appreciated.

I am running on Server 2003 64 (although the same thing happens when deployed on a Server 2003 32 machine)

Thanks

B.

View 2 Replies View Related

Step-by-step Deployment Of Single-user Database App?

Mar 2, 2008

Hi!

I hope the answer is as simple as the question -- but after reading all the documentation I could find (understand?) and a lot of posts here, I'm no closer to achieving the goal.

I have a Visual C# app, DAYTRACKER, developed in VS2005. It uses a database with several tables constructed using SQL Server 2005 Developer Edition.

I want to deploy the app plus the database plus SQL Express to another machine, to be used by a single user (the administrator) with no need for network connectivity of any kind.

What I have so far is:
1. The application is successfully deployed from a CD-ROM, having used the Publish process within VS2005, and opens on the new machine -- without database connectivity, however.
2. SQL Express is successfully deployed (it deployed as a 'prerequisite' when I went through the Publish process in VS2005)
3. I manually copied the database's .mdf and .mdl files, using SQL Server Managers 'Copy Database' function, then transferred the copies to the new machine into the ..MSSQL.1MSSQLdata folder (where they appear along with the master.mdg, mastlog.ldf etc files)

Now, the DAYTRACKER application's DAYTRACKERConnectionString under 'Settings' in the VS2005 studio reads 'Data Source=DELL3;Initial Catalog=DayTracker;Integrated Security=True' (which are the appropriate parameters for the machine, DELL3, on which I wrote the program.)

The problem, of course, is that SQL Express on the new machine doesn't connect the application to the database. When I go to the 'SQL Server Configuration Manager' and go to the 'SQL Server 2005 Services' and double-click on the 'SQL Server (SQLEXPRESS)' icon (the service is running) and the user is logged on using 'Local System Account'. Under the 'Service' tab the Host Name is 'MUSIC' (which is the name of the new machine I've installed the app onto -- which of course is not the name - DELL3 - that the app's connection string is expecting). Under the 'Advanced' tab, I've tried correcting the name of the Startup Parameters default .mdf and .mdl entries to ..DayTracker.mdf and ..DayTracker_log.mdl, but the server won't start up after I make the changes.

What I'm hoping for: a step-by-step way of doing this type of deployment, preferable getting it all onto one CD-ROM, and installing it on the new machine so that it all works seamlessly from the start, not requiring any 'tweaking' of the SQLServer Express settings by the end-user.

But I'll take pretty much anything that fixes the specific db connectivity problem I've described.

Thank you very much.

John F.

View 11 Replies View Related

(Item Lookup Error! Hr=80040e21, HrDesc=Multiple-step OLE DB Operation Generated Errors. Check Each OLE DB Status Value, If Av

Jan 31, 2007

Hi,

I am using ATL COM library application. It is using sql data base for fetching the records. Some times, i get the following error. could you please let me know, why this happens? This is not reproduceble every time.

(Error! hr=80040e21, hrDesc=Multiple-step OLE DB operation generated errors. Check each OLE DB status value, if available. No work

Here is the code to connect to database which i am using.

CDataSource db;
CDBPropSet dbinit(DBPROPSET_DBINIT);

dbinit.AddProperty(DBPROP_AUTH_INTEGRATED, OLESTR("SSPI"));
dbinit.AddProperty(DBPROP_INIT_CATALOG, (const char *)bDatabase);
dbinit.AddProperty(DBPROP_INIT_DATASOURCE, (const char *)bServer);
dbinit.AddProperty(DBPROP_INIT_LCID, (long)1033);
dbinit.AddProperty(DBPROP_INIT_PROMPT, (short)4);
dbinit.AddProperty(DBPROP_INIT_TIMEOUT, (short)150);
hr = db.Open(_T("SQLOLEDB.1"), &dbinit);
if (FatalError(hr, "db.Open", buf))
{
*iErrorCode = hr;
return S_OK;
}



Any help, appreciated.



Thanks,

Satish

View 1 Replies View Related